You are on PERI's international website. Click here to switch to PERI USA. Click here to view all PERI websites.

Sandelermöns Waterworks, Germany

項目數據

地點: Sandelermöns, 德國

  • Waterworks with circular tanks for 20.000 m³ water

要求

  • Forming of circular tanks, walls and columns with a minimum of material and time requirements

客戶

Contractor: Ludwig Freytag GmbH & Co. KG, Wilhelmshaven Office
Field Service: PERI Oldenburg and PERI GmbH, Germany

客戶的利益

  • Fast and accurate shuttering of circular containers with RUNDFLEX Plus
Ewald Jelten, Foreman, Wasserwerk Sandelermöns
Ewald Jelten
Foreman

With the RUNDFLEX Plus, we only needed half the time compared to conventional circular formwork. This tried-and-tested system reduces material requirements and the work involved, and includes all accessories. The safety equipment is a great advantage and easy to assemble. My team have had absolutely no problems using the RUNDFLEX Plus - it really is good.

派利方案

The PERI RUNDFLEX Plus circular formwork, in conjunction with TRIO panel formwork and PERI UP reinforcement scaffolding units, provided the most cost-effective solution for the construction team. It enabled the external wall sections to be shuttered, reinforced and concreted in four 25 m long casting segments. Adjusting the circular formwork elements took place on site. This saved on transportation costs and allowed the internal walls to be constructed using the same set of formwork.

Due to the rigid waler system, no additional distribution walers are required for the RUNDFLEX Plus. This simplified the handling and ensured enormous time savings. The BFD alignment coupler from the TRIO product range guaranteed fast and neat element connections and also bridged filler timber compensations up to 10 cm.

For the straight intermediate walls, TRIO 330 elements were used horizontally. With TRIO column elements, the twelve reinforced concrete columns could be quickly shuttered and concreted. In the process, PERI UP reinforcement scaffolding units provided safe working platforms for handling the formwork, carrying out reinforcement work and concreting. These could be moved on guide rollers as well being transported as complete units with the crane.

派利使用中的系統