HKIA T1 Annex and Car Park 4 Expansion

項目數據

地點: Hong Kong, 香港

Hong Kong International Airport plans to expand and address ever growing number of airport customers, this project will provide an additional passenger area and a car park.

Estimated completion year: 2022

要求

  • To construct the cantilever slab in height without using falsework from ground
  • To continue construction works above while providing safe traffic access below

客戶

Leighton Asia

客戶的利益

  • Reduced falsework requirement to cantilever slab structure in 48 meters above ground
  • Reduced labour costs
  • Provided clear opening below for traffic while continuing construction works above
  • Minimal tower components, easy to erect and dismantle

派利方案

  • SB Bracket Cantilever Platform assembly in ground for optimum safety
  • Alpha 300kN and VST 700kN single leg load to carry falsework and concrete load

派利使用中的系統