You are on PERI's international website. Click here to switch to PERI USA. Click here to view all PERI websites.

Albian Sands, Canada

項目數據

地點: Fort McMurray, 加拿大

Production plant for the extraction of oil sand in an open pit mine.

Construction period: 2006-2010

要求

  • massive foundations and rectangular columns
  • beams of 4 m in height
  • use of self-compacting concrete with high concrete pressures

客戶

Ledcor Industries, Fort McMurray

客戶的利益

  • falsework and working platform with one system
  • flexible adaptation to high loads and complex structural geometry
  • falsework and slab formwork perfectly matched
  • simple adjustment with system components thanks to metric grid
Albian Sands Statement - Denis Dubeau, Site Manager
Denis Dubeau
Site Manager

There are many shoring systems and also a lot of working scaffold on the market.  But PERI UP is the only system which equally satisfies both aspects.  In particular, the high load-bearing capacity impressed me.

派利方案

  • planning and delivery of formwork and scaffolding from one place
  • VARIO and TRIO for walls, MULTIFLEX for slabs and PERI UP as falsework
  • The birdcage scaffold with a basic grid of 1.50 m x 1.50 m could be halved/doubled to 75-cm and 3.00-m widths in areas of high loads, stair access integrated in falsework/working platform.

派利使用中的系統